How to Sign Off a Weighing System: 20% / 50% / 100% Over Three Days (Corner Test and Record Sheet)

Acceptance is not "the number moves, so it works". The only method that actually decides the question is: load three points with test weights, repeat on three consecutive days, then run one corner test. This page gives the actions, the record sheet, the pass criteria and what to do when the test fails.

Stuck at one step, or unsure which points to test:

+86 183 5123 8137

On a phone, the button opens the dialler.

Short answer: load 20% / 50% / 100% of capacity with test weights, record the reading under load and the zero after unloading, repeat on three consecutive days — nine readings in all — then run a corner test with the weights at each of the four supports. The three points check linearity, the three days check repeatability, and the corner test checks that the load is shared.

Why three load points and three days?

Short answer: faults in a weighing system fall into two groups — wrong straight away and slowly changing. One test finds only the first; testing only the working point finds only what is wrong near that point.

These criteria are quoted from public technical literature. The limits themselves are confirmed against the indicator manual and the site conditions; this page publishes no generic accuracy figure.

What has to be ready before the test?

Checklist before the acceptance test
Item Requirement What happens without it
Test weights Enough to reach 20% / 50% / 100% of capacity; they can be added in stages Only substitutes are left, and the readings cannot be traced
A place to stand the weights A weight platform under the vessel — something to allow for when a new vessel is designed The weights cannot be placed steadily, so the readings are not trustworthy
Record sheet Laid out by day, load point and reading, as in the next section After three days there is nothing to compare, so the test may as well not have been run
Site conditions Temperature, wind and whether the vessel was just filled, written down on the day A difference between readings cannot be traced to a cause
Indicator settings Zero-on-power-up switched off; a threshold set for automatic zero tracking The indicator erases the data during the test itself

The weight platform is the item most often missed. On an older vessel that has none, the only route is to assess adding one by welding — and before any welding, confirm that the welding current cannot pass through the load cell.

What does the three-day record sheet look like?

Short answer: one sheet holds it. Load points run across, day and repetition run down. What matters is not the layout but that the same sheet, the same weights and the same loading order are used on all three days.

Record sheet layout (example: 10 t capacity, weights applied at 2 t / 5 t / 10 t)
Day Load point Reading under load Zero after unload Note (temperature / wind / recent fill)
Day 1 20% — — —
Day 1 50% — — —
Day 1 100% — — —
Day 2 The same three points — — —
Day 3 The same three points — — —

Each cell takes the stable value under load and the value the indicator returns to after unloading. Nine readings over three days; the spread of the same load point across the three days is the repeatability.

How is the corner test run?

Short answer: with the vessel empty and then at a working load, put the weights near each of the four supports in turn and see whether the four readings agree.

  1. Record one reference reading with the vessel empty.
  2. Place the weights in turn above each of the four supports (the corners) and record the reading each time.
  3. Compare the spread between the four readings.

What a large spread means: the four supports are not sharing the load. Check two things first —

The permitted spread is judged by the method in the indicator manual. No generic figure is given here, so that nothing on this page reads as a commitment.

Which three causes explain most failed tests?

Three typical failures and what to do first
Symptom Cause First action
All three points off in the same direction (all low or all high) Weight is being bypassed: hard-piped connections, a platform or ladder welded to the vessel, restraint bolts bottomed out Check piping and restraints first, in the order given in the companion note, Eight pitfalls that stop a system from reading right after installation
Middle point right, both ends off Linearity: the capacity step is too small, or the modules in the system do not all have the same capacity Check that every module carries the same rated capacity
Good on day one, drifting by day three Moisture, an unstable supply, or stress release Check the junction box for moisture and check the supply voltage (H7 and H8 in the same note)

How do I keep watch after sign-off, one zero reading a day?

Short answer: once the system is in production, record the empty zero once a day. After three months, plot the curve and read its shape — the quickest way to tell "damaged" from "drifting".

Three shapes of the daily zero curve and what to do
Curve shape Reading Suggested action
Step change Jumps one step at a single moment and then stays there; usually damage from an impact, an overload or moisture Replace the module with one of the same specification
Smooth creep Continuous, slow, monotonic rise — long-term drift (stress relaxation in the element plus ageing of the strain-gauge adhesive), unrelated to temperature or impact Compensate or recalibrate first; do not replace a whole batch in a hurry
Swing with temperature Tied to temperature, not long-term drift Check the environment and the compensation settings

Impact damage = step change; long-term drift = smooth creep; step change → replace the module; smooth creep → compensate or recalibrate first.

This reading of the curve is quoted from public technical literature and can be copied straight into the acceptance record or the asset register.

Which four mistakes are most common?

  1. Testing only the working point: the vessel normally runs at 30%, so only 30% is tested. A linearity fault near the top of the range is then never found.
  2. Testing for one day only: the day-one figures look good and the sheet is signed. Moisture, stress release and supply problems need several days to show.
  3. Using substitutes instead of test weights: a material of assumed weight stands in for the weights. The readings cannot be traced, and when something goes wrong nobody owns it.
  4. Forgetting to switch off zero-on-power-up: the indicator wipes the data during the test, and the three days are wasted.

Where do the facts on this page come from?

This page is a general technical note. It makes no performance commitment for any particular project; the limits are confirmed against the indicator manual and the site conditions.

Still not passing? What do we need to judge it?

Send us: the module model and the number of modules, the indicator model, the capacity, the three readings, the spread across the four supports, the site temperature and whether the unit stands outdoors, whether the connections are hard pipe or flexible hose, and the vessel dead weight and product weight.