Which six numbers do I need before sizing?
| Information | Why it is needed |
|---|---|
| Vessel weight | This is the dead load and it has to be counted. It is the item most often left out. |
| Weight of the attachments | Agitator motor, jacket, insulation, platform and ladders are all dead load. |
| Product weight at full fill | This is the live load. Use the full fill, not the usual batch. |
| Number of support points | It sets the module count, and the module count goes straight into the formula. |
| Product characteristics | Corrosiveness and temperature decide stainless steel or nickel-plated; whether the area is hazardous decides the configuration. |
| Distance from the modules to the indicator | A long run drops the excitation voltage, which decides 4-wire or 6-wire. |
How much capacity does each module need?
Direct answer: with the rule used across the industry (source: public technical literature):
dead load + live load ≤ rated capacity × number of modules × 70%
The 70% is the safety margin normally applied in the industry. It already covers the parts that are not calculated exactly: eccentric load, shock and wind load.
Use the formula backwards
First work out what each module actually carries:
load per module = (vessel weight + attachments + product at full fill) ÷ number of modules
Then put that figure against rated capacity × 70% and take the next capacity step up.
How do the three worked examples come out?
Example 1: 500 L reactor on 3 support feet
| Item | Value |
|---|---|
| Vessel weight | About 300 kg (agitator and jacket included) |
| Product at full fill | About 400 kg |
| Support feet | 3 |
Work out: (300 + 400) ÷ 3 = 233 kg per module.
Check:
- 300 kg step: 300 × 3 × 70% = 630 kg < 700 kg — not enough.
- 500 kg step: 500 × 3 × 70% = 1050 kg ≥ 700 kg — enough.
Result: take the 500 kg step. Do not take the 300 kg step: 233 kg per module looks sufficient, but it does not pass the 70% check.
Example 2: 5 t vessel on 4 support feet
| Item | Value |
|---|---|
| Vessel weight | 5 t (insulation and platform included) |
| Product at full fill | 8 t |
| Support feet | 4 |
Work out: (5 + 8) ÷ 4 = 3.25 t per module.
Check:
- 3 t step: 3 × 4 × 70% = 8.4 t < 13 t — not enough.
- 5 t step: 5 × 4 × 70% = 14 t ≥ 13 t — enough (about 1 t spare: tight, but it holds).
- 8 t step: 8 × 4 × 70% = 22.4 t — enough, with a wide margin, at a higher cost.
Result: take the 5 t step. Where there is agitator shock or wind load on site, go up to the 8 t step.
Example 3: 30 t tank, also on 4 feet
| Item | Value |
|---|---|
| Vessel weight | 30 t |
| Product at full fill | 50 t |
| Support feet | 4 |
Work out: (30 + 50) ÷ 4 = 20 t per module.
Check:
- 20 t step: 20 × 4 × 70% = 56 t < 80 t — not enough.
- 30 t step: 30 × 4 × 70% = 84 t ≥ 80 t — enough.
Result: take the 30 t step.
Now change the module count: on the same vessel with only 3 feet, 80 ÷ 3 = 26.7 t per module, and the 30 t step gives 30 × 3 × 70% = 63 t < 80 t — not enough, so the step has to go up to the 50 t. One module fewer can mean one capacity step higher. That is why the module count is not something to cut for convenience.
How many modules should the vessel have?
Direct answer: take the number of support points, not the number of modules you would like to save.
| Situation | How to take it | Basis |
|---|---|---|
| The vessel already has support feet | 3 feet, 3 modules; 4 feet, 4 modules — the actual number of support points | Public technical literature |
| A new vessel, vertical cylinder | Three-point support is more stable; where wind load, sway or vibration is present, four-point support is advisable | Public technical literature |
| Agitation or side impact | Four-point, with limit stops | Public technical literature |
More modules is not automatically better: a larger count allows a smaller capacity per module, but every module then has to share the load evenly, levelling the mounting faces gets harder, and acceptance gets harder to pass.
How is a set of modules configured?
Direct answer: the modules in one system are not all the same: 1 fixed + 1 semi-floating + the rest full-floating.
- Fixed: it holds the position and is the reference for the whole system.
- Semi-floating: it takes up movement in one direction.
- Full-floating (also called floating): it takes up thermal expansion and installation tolerance.
If every module in the set is bought as fixed, the vessel has no room to expand or to deflect under load, and the modules are loaded sideways — the numbers will be wrong at the least, and the load cell can be damaged at the worst. On the Selection & Resources page this is the "tilted load / side load" fault among the eight installation faults.
Which material and wiring should I choose?
| Site condition | What to choose | Reason |
|---|---|---|
| Wet, washed down, corrosive atmosphere | Stainless steel, hermetically sealed (a model whose documentation states its protection) | A welded seal is the basis of moisture protection, but the cable entry and the junction box have to match it |
| Indoors, dry environment | Alloy steel, nickel-plated | Lower cost; a plated finish still has to be checked against the duty where a strong corrosive medium is present |
| Long run from the modules to the indicator | 6-wire (with +sense / −sense) | The sense wires compensate the excitation drop over a long cable; a short run is fine on 4-wire |
| Hazardous area | Explosion-proof version (the exact selection is confirmed against the duty) | The configuration follows the area classification on site; the wording of the marking follows the company position |
What are the four common miscalculations?
- Sizing by volume. "A 5 m³ tank is 5 t." Product density varies widely (water 1.0, feed 0.5–0.7, mineral powder 1.5 and above), so sizing by volume can be far out.
- Forgetting the vessel weight. Only the product is counted. An empty vessel alone weighs from a few tonnes to tens of tonnes; leave it out and the module is certain to be undersized.
- Not applying the 70%. Total weight divided by the module count is bought as the rated capacity. There is no margin, so eccentric load or shock overloads it.
- Cutting the module count. 3 modules on 4 feet, or 4 modules reduced to 2. The load is uneven and acceptance will not pass.
Does this sheet settle the sizing?
| Item | Your value |
|---|---|
| Vessel weight (attachments included) | ____ t |
| Product weight at full fill | ____ t |
| Number of support points | ____ modules |
| Load per module worked out | ____ t (the first two added together ÷ module count) |
| Capacity step taken (next one up) | ____ t |
| Environment (indoor or outdoor, washed down, corrosive) | ____ |
| Distance from the modules to the indicator | ____ m |
| Is a hazardous area involved? | Yes / No |
| Is there a test-weight platform? | Yes / No (without one, the vessel cannot be checked with weights later) |
Where does the information on this page come from?
- Public technical literature: the industry rule (dead load + live load ≤ rated capacity × number of modules × 70%), the module count rules, when three-point and four-point support apply, the fixed / semi-floating / full-floating arrangement, and the role of the sense wires in a 6-wire cable.
- Company product documentation: the capacity steps of each model, the material wording, the wiring standard, and the explosion-proof configuration (the exact selection is confirmed against the duty).
- What this page adds: the three worked examples, the module-count difference, the four miscalculations and the sizing sheet — these are arranged from the two sources above and change no fact.
This page is general technical information, not a commitment for a specific project; the final selection is confirmed against the duty and the documentation supplied with the goods.
Sizing is done — what should I look at next?
Tap to dial: +86 183 5123 8137
- Eight installation faults: check order →
- Replacing a load cell: 5 places it goes wrong →
- All models, grouped by capacity: 13 models and 2 structure types →
- Selection & Resources: four duties, how to select, how to install, how to verify →
- FAQ: module count, calibration, warranty →
- HY-UW: 5 kg to 500 kg in 10 steps, stainless steel, IP68 →
- HY-CWC-M: 0.5 t to 20 t, column type, stainless steel, IP68 →